HomeProjectsMurra Warra Windfarm

Project Name:  Murra Warra Windfarm – STAGE 1

Client Name: Symal (formerly Civilex)

Project Description: Murra Warra Windfarm located 25kms from Horsham.
The Murra Warra Wind Farm is being constructed in two stages – with Stage 1 comprising 61 turbines in the south west of site, and Stage 2 comprising 55 turbines towards the north east of site.
Once complete, the wind farm will be able to produce 429MW of electricity – enough clean energy to power approximately 420,000 homes and save roughly 1.7 million tonnes of carbon emissions each year.
Foundation reinforcing required accurate radius bending (36mm dia. Bar), pre-slinging of bundles, creative logistical solution to optimise efficiency, reduce costs and ensure continuity of supply on an aggressive construction program. 

Tonnage: 1800T

Construction workers laying out reinforcing bars installation of Reomesh Completion of reinforcing bar and mesh